Integrated Licensing Process Timeline
- February 10, 2011: Districts File Pre-Application Document (PAD) and Notice of Intent (NOI) to relicense the Project
- FERC conducts scoping
-
- April 8, 2011: FERC issues Scoping Document 1 (SD1)
- May 2011: FERC holds site visit and public scoping meetings
- July 25, 2011: FERC issues Scoping Document 2 (SD2)
- July 25, 2011: Districts file Proposed Study Plan (PSP)
- November 22, 2011: Districts file Revised Study Plan (RSP)
- December 22, 2011: FERC issues its Study Plan Determination (SPD)
- May 24, 2012: FERC Director issues Study Dispute Determination (SDD)
- January 17, 2013: Districts issue Initial Study Report (ISR)
- November 26, 2013: Districts file Draft License Application (DLA)
- January 6, 2014: Districts issue Updated Study Report (USR)
- April 28, 2014: Districts file Final License Application (FLA)
- October 11, 2017: Districts issue Amendment to Final License Application (AFLA)
- February 11, 2019: FERC issues Draft Environmental Impact Statement (DEIS)
- July 7, 2020: FERC issues Final Environmental Impact Statement (FEIS)
- Future Date: FERC issues new license with new terms and conditions